Wednesday, October 2, 2013

Day 3 (Wednesday) - Framing, floor, countertop template

Report:
  1. New half wall is framed in.
  2. New shower sub-floor is in.
  3. New studs sistered to the one(s) with dry rot shaved off.
  4. Shower cubby will go into the half-wall because there isn't room in the side wall with the hall bathroom's plumbing. 
  5. New exhaust fan switch will joining the heater switch in the heater switch location. Switch box will be changed to plastic. 
  6. The fabricator came & made a template for the counter-top.
Net net - Construction seems slower than demo, but on schedule (2.5 wks).