- The mud pan is in.
- The shower curb is in
- The moisture barrier & cement backer board is up
- The shower valve & shower head are in.
- Apparently the nailgun, used to install backer board on the shared wall studs, knocked some of the grout out of the hallway bathroom's tile, because I found shards of it in the tub as well as holes in the grout lines. So a little grout repair is going to be needed there.
Sunday, October 6, 2013
Day 5 (Friday) - Mud pan, backer board, more plumbing.
Today was a long day, almost 12 hrs (9:30am - 8pm)!